Building Control

Demolitions

Summary

Building Control are responsible for the control of demolition of buildings in excess of 49.5 cubic metres.

 

Attachments

Adobe Acrobat's portable document format (pdf). To view these files you will need to have the Adobe Acrobat Reader installed on your computer. This can be downloaded free at Adobe's web site| [External].

 

Demolition Notice (pdf 150kb)|

 

 

Demolition

When intending to demolish a building in excess of 49.5 cubic metres, official notice must be given to Building Control, usually a minimum of six weeks prior to the intended start date. You can request a copy of our standard demolition notification form or alternatively download a copy.

 

Demolition Notice (pdf 150kb)|

Building being demolished
In order for us to process this application you must also provide a 1:1250 location plan clearly indicating the buildings to be demolished, all adjacent properties and existing drainage systems to be sealed, together with a copy of the demolition contractor's method statement indicating safe methods of demolition.

 

Within 6 weeks of receiving this completed application, we will issue a Demolition Notice setting out a number of conditions that have to be complied with during the demolition works necessary to maintain public safety and public amenity.

 

Building Control may also consult with the Environmental Health and Planning departments, Leicestershire County Council Highways, and Leicestershire Fire and Rescue Service prior to the issuing of a demolition notice.

 

You should also notify all service providers such as gas, electric and water by sending them a copy of the notification form and location plan, in order that they may arrange with yourselves for their services to be safely disconnected.

 

 

 